Quick update on bathroom renovations

Progress has been slow this week as we have had to wait for things to dry between layers.

doors on

The doors are now on so we can get an idea now of the finished look from the bedroom.

Plastering has been completed.

plastering and floor skimmingThe lights were used to dry things out between layers.

The tiles have been delivered.

tilesThe tiler has his tools prepared.

The waterproof coat has been applied, twice.

shower recess

Next step is the actual tiling.

 